08/18/02
JAMES
GELUSO
Skagit Valley Herald
The Skagit Public Utility District
could construct a pump house for its
pipeline project next summer if the
permits are issued in time.
The district plans to build a
pipeline to draw water from the Skagit
River east of Sedro-Woolley. The water
will be pumped 1,300 feet through an
underground pipeline to the Judy
Reservoir, which is about 400 feet above
the river on the side of Cultus
Mountain.
The project is expected to cost $4
million to $6 million.
The project will provide a more
stable source of water than the four
Cultus Mountain streams the district
depends on for its main water system,
said Ken Kukuk, general manager of the
utility.
In the short term, it
will allow the district to refrain from
drawing water from the streams when they
are low, leaving more water for fish
passage.
While both
the streams and the Skagit River are
subject to minimum flow levels, the
river’s flow increases and decreases
throughout the day, in part because of
the release of water from Puget Sound
Energy’s Lower Baker Dam at Concrete.
The utility can draw water from the
river when it’s high, Kukuk said.
“We have to learn to manage the
resource, and that’s what we’re all
getting practice in these days,” he
said.
The district’s main water system
provides water to Burlington, Mount
Vernon, Sedro-Woolley and much of the
surrounding areas. It also manages other
small water systems throughout the
county, but those have separate water
sources.
The project will allow the utility to
use less water from the Anacortes system
as well, Kukuk said. In drought
conditions, the utility sometimes
purchases water from Anacortes because
that system draws water from the Skagit
River, a more stable supply than the
mountain streams.
The district also uses Anacortes
water for its pipelines in the Bay View
area, he said. The district eventually
will shift to using its own water for
that system. The district probably will
always buy water from Anacortes for its
service area on south Fidalgo Island, he
said.
Construction of the pump house is
subject to a “fish window,” a
limited period of time in which work can
be done in the river. But Kukuk said he
expects the pump house work can be done
in a single summer if permits come
through.
The district already has a shorelines
permit from Skagit County. The U.S. Army
Corps of Engineers has sent information
on the permit to other agencies for
comments.
The pump house will include five
900-horsepower pumps, each capable of
pushing about 7.5 million gallons a day.
Only rarely would all five be used at
once, Kukuk said.
After the pipeline is finished, the
district is looking at expanding its
filtration plant so it can process more
water, Kukuk said.